Hard rock mill version 1.001
This is the 1st setup (we have taken it down and setup again at new site) of the hard rock mill. It current capacity is 250lbs per hour. It takes about 8 hours to run a ton. I believe the table and jaw crusher/roller mill will do about 1tph. The bottle neck in the system is the impact mill. Will upgrade on a later mill version. We just need to add a mini conveyor to transfer material from the jaw crusher/roller discharge to the auger feed bin and a larger conveyor to feed the jaw crusher. That will save someones back.... mine; and complete the system until adding a 10x14 jaw crusher to feed the 6x4 jaw/roller mill.
-